Marrs Middle School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  Morrissey Engineering

Contractor:  Downs Electric, Inc. and Hiller Electric Company
Related Documents
  •  Marrs Middle
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Marrs Middle School
Substantial completion was approved by the Board of Education on February 17, 2016. Project closeout documents have been submitted and transmitted to OPS. The remaining work on the card access control system is complete and the contractor is in the closeout phase which involves punch list items.
Read More »

Project Budget

Marrs

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$112,973

$99,330

$13,643

$96,950

Construction

$947,718

$970,740

($23,023)

$801,344

Misc.

$6,276

$0

$6,276

$0

Contingency

$188,288

$0

$188,288

$0

TOTAL:

$1,255,255

$1,070,070

$185,185

$898,294