Northwest High Magnet

Scope

8204 Crown Point Avenue
Omaha, NE 68134
Phone: (402) 557-3500

Northwest High School is scheduled to get fire, life safety, security and technology upgrades; capital improvements to the existing building as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  KAI Design & Build

Contractor:  CM@R - Vrana Construction
Related Documents
  •  Northwest High
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Northwest Magnet High School
The construction work for the new gymnasium addition was complete in August 2017. Interior finish work on the new administrative addition was complete in August 2017. The final construction phase is ongoing and is scheduled to be complete in September 2017.
Read More »

Project Budget

Northwest

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$1,024,371

$937,200

$87,171

$840,211

Construction

$12,193,856

$12,275,549

($81,693)

$10,926,807

Misc.

$56,909

$62,387

($5,478)

$36,319

Contingency

$0

$0

$0

$0

TOTAL:

$13,275,136

$13,275,136

$0

$11,803,337