Central High

Scope

124 North 20th Street
Omaha, NE 68102
Phone: (402) 557-3300

Central High School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  Alley-Poyner Macchietto Architecture 
 
Contractor:  McGill Restoration  &  Mark VII Enterprises
Related Documents
  •  Central High
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Central High School
The fire alarm system reached substantial completion in January 2017. The access control system along with the door hardware modifications was complete in July 2017. The construction work is ongoing with exterior masonry restoration work and is scheduled to be complete in November 2017.
Read More »

Project Budget

Central

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$457,553

$383,500

$74,053

$312,099

Construction

$4,600,954

$4,450,426

$150,528

$3,543,463

Misc.

$25,419

$0

$25,419

$0

Contingency

$0

$0

$0

$0

TOTAL:

$5,083,926

$4,833,926

$250,000

$3,855,562