Burke High

Scope

12200 Burke Blvd.
Omaha, NE 68154
Phone: (402) 557-3200

Burke High School is scheduled to get fire, life safety, security and technology upgrades; capital improvements to the existing building as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  KPE Engineers

Contractor: CM@R - The Weitz Company

Related Documents
  •  Burke High
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Burke High School
The Phase 1 interior building construction work in the cafeteria was complete in August 2017. The new multipurpose room construction is ongoing with concrete footings and exterior masonry work. Site concrete work located on the East side of the building is scheduled to be complete in August 2017.
Read More »

Project Budget

Burke

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$724,827

$686,600

$38,227

$556,600

Construction

$8,788,543

$8,713,275

$75,269

$1,876,673

Misc.

$40,268

$153,764

($113,496)

$20,544

Contingency

$0

$0

$0

$0

TOTAL:

$9,553,638

$9,553,638

$0

$2,453,816