Burke High

Scope

12200 Burke Blvd.
Omaha, NE 68154
Phone: (402) 557-3200

Burke High School is scheduled to get fire, life safety, security and technology upgrades; capital improvements to the existing building as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  KPE Engineers

Contractor: CM@R - The Weitz Company

Related Documents
  •  Burke High
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Burke High School
The Phase 1 interior building construction work in the cafeteria is ongoing and is scheduled to be complete in August 2017. The new fire sprinkler system and interior painting has started in June 2017. The new multipurpose room construction work has started in June 2017. Site concrete work located on the East side of the building is scheduled to begin in July 2017.
Read More »

Project Budget

Burke

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$724,827

$679,600

$45,227

$538,407

Construction

$8,788,543

$8,720,672

$67,871

$883,028

Misc.

$40,268

$153,366

($113,098)

$18,037

Contingency

$0

$0

$0

$0

TOTAL:

$9,553,638

$9,553,638

$0

$1,439,472