Skinner Magnet Elementary

Scope

4304 North 33rd Street
Omaha, NE 68111
Phone: (402) 453-6857

Skinner Elementary School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  Carlson West Povondra

Contractor:  Elkhorn West Construction & Downs Electric Inc.
Related Documents
  •  Skinner Magnet Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Skinner Elementary School
The construction work on the classroom door hardware is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work has started in May 2017 and this work is scheduled to be complete in July 2017.
Read More »

Project Budget

Skinner

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$18,325

$14,035

$4,290

$12,047

Construction

$153,725

$189,574

($35,849)

$136,289

Misc.

$1,018

$0

$1,018

$0

Contingency

$30,541

$0

$30,541

$0

TOTAL:

$203,609

$203,609

$0

$148,336