Pawnee Elementary

Scope

7310 South 48th Street
Omaha, NE 68157-2299
Phone: (402) 734-5011

Pawnee Elementary School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  Alvine Engineering

Contractor:  Meco-Henne Contracting
Related Documents
  •  Pawnee Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Pawnee Elementary School
The construction work is in progress on the fire sprinkler upgrades, access control system, and new storm safe area.
Read More »

Project Budget

Pawnee

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$73,532

$73,532

$0

$38,866

Construction

$616,848

$616,708

$140

$140,524

Misc.

$4,085

$4,225

($140)

$1,940

Contingency

$122,553

$22,553

$100,000

$0

TOTAL:

$817,017

$717,017

$100,000

$181,330