Masters Elementary

Scope

5505 North 99th Street
Omaha, NE 68134-1599
Phone: (402) 572-1027

J.G. Masters Elementary School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  Jackson-Jackson & Associates

Contractor:  Midwest DCM, Inc.
Related Documents
  •  Masters Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Masters Elementary School
Substantial completion was approved by the Board of Education on December 12, 2016. Project closeout documents have been submitted and transmitted to OPS.
Read More »

Project Budget

Masters

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$83,078

$83,078

$0

$83,078

Construction

$1,176,724

$1,176,724

$0

$1,176,724

Misc.

$6,075

$6,075

$0

$6,075

Contingency

$0

$0

$0

$0

TOTAL:

$1,265,878

$1,265,878

$0

$1,265,878