Columbian Elementary

Scope

330 South 127th Street
Omaha, NE 68154-2300
Phone: (402) 697-1433

Columbian Elementary School includes a complete replacement of the existing school as identified in the 2014 OPS Facilities Capital Plan.

General Information

 Architect:  The Schemmer Associates 

Contractor:  

School Bond Updates

Most Recent

Columbian Elementary School
The Educational Specifications package was approved by the Board of Education on June 19, 2017. The project is now in the Schematic Design phase.
Read More »

Project Budget

Columbian

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$1,166,197

$1,166,197

$0

$67,667

Construction

$9,653,523

$9,653,523

$0

$0

FF&E

$917,085

$917,085

$0

$0

Misc.

$64,789

$64,789

$0

$0

Contingency

$1,943,663

$1,943,663

$0

$0

Site Acquisition

$129,577

$129,577

$0

$5,843

TOTAL:

$13,874,834

$13,874,834

$0

$73,509