Castelar Elementary

Scope

2316 South 18th Street
Omaha, NE 68108
Phone: (402) 344-7794

Castelar Elementary School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:   Alvine Engineering

Contractor:  Downs Electric Inc.
Related Documents
  •  Castelar Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Castelar Elementary School
The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.
Read More »

Project Budget

Castelar

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$16,231

$10,420

$5,811

$8,627

Construction

$586,157

$603,376

($17,220)

$588,375

Misc.

$902

$0

$902

$0

Contingency

$27,051

$16,544

$10,507

$0

TOTAL:

$630,340

$630,340

$0

$597,002