Benson West Elementary

Scope

6653 Maple Street
Omaha, NE 68104-3995
Phone: (402) 554-8633

Benson West Elementary School is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:  Carlson West Povondra

Contractor:  Roloff Building Group
Related Documents
  •  Benson West Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Benson West Elementary School
The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on July 24, 2017.
Read More »

Project Budget

Benson West

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$129,509

$129,509

$0

$85,139

Construction

$1,601,438

$1,776,908

($175,470)

$1,666,263

Misc.

$7,195

$10,263

($3,069)

$3,069

Contingency

$215,849

$37,310

$178,539

$0

TOTAL:

$1,953,991

$1,953,991

$0

$1,754,471