Ashland Park Robbins Elementary

Scope

5050 South 51st Street
Omaha, NE 68117
Phone: (402) 734-6001

Ashland Park-Robbins is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:   Alvine Engineering

Contractor:  Meco-Henne Contracting
Related Documents
  •  Ashland Park Robbins Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Ashland Park-Robbins Elementary School
The construction mobilization started in April 2017. The scope of work consists of fire alarm upgrades, door hardware replacement and access control system which will begin in June 2017.
Read More »

Project Budget

Ashland Park / Robbins

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$163,218

$163,218

$0

$81,350

Construction

$1,369,220

$1,169,220

$200,000

$0

Misc.

$9,068

$9,068

$0

$0

Contingency

$272,030

$172,030

$100,000

$0

TOTAL:

$1,813,536

$1,513,536

$300,000

$81,350