Ashland Park-Robbins is scheduled to receive fire, life safety, security & technology upgrades as identified in the 2014 OPS Facilities Capital Plan.

General Information

Architect:   Alvine Engineering

Contractor:  Meco-Henne Contracting
Related Documents
  •  Ashland Park Robbins Elementary
Table that lists the contents of the current directory
FilenameSize
  
  
  
  
  
  
  
  
  
  
  
Max file size allowed:
786.81 MB
File extensions allowed:
*.swf, *.jpg, *.jpeg, *.jpe, *.gif, *.bmp, *.png, *.svg, *.ttf, *.eot, *.woff, *.doc, *.docx, *.xls, *.xlsx, *.ppt, *.pptx, *.pdf, *.txt, *.xml, *.xsl, *.xsd, *.css, *.zip, *.rar, *.template, *.htmtemplate, *.ico, *.avi, *.mpg, *.mpeg, *.mp3, *.wmv, *.mov, *.wav
  • Uploaded % ( ) Total
  • Uploaded files: % () Total files:
  • Uploading file:
  • Elapsed time:  Estimated time:  Speed:

QuickDocs v7.0.6

School Bond Updates

Most Recent

Ashland Park-Robbins Elementary School
The bid/award was approved by the Board of Education on March 6, 2017. The construction mobilization is scheduled to begin in April 2017.
Read More »

Project Budget

Ashland Park / Robbins

BUDGET

PROJECTED COSTS

OVER/UNDER

ACTUALS

Design

$163,218

$163,218

$0

$76,649

Construction

$1,369,220

$1,169,220

$200,000

$0

Misc.

$9,068

$9,068

$0

$0

Contingency

$272,030

$172,030

$100,000

$0

TOTAL:

$1,813,536

$1,513,536

$300,000

$76,649