Omaha Public Schools site for all news related to school bond projects.

OPS Property – 32nd & Burt Street

The Educational Specifications package is scheduled to be submitted to the Board of Education for approval on March 20, 2017.  The next phase of the project is Schematic Design.

Adams Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Ashland Park-Robbins Elementary School

The bid/award was approved by the Board of Education on March 6, 2017. The construction mobilization is scheduled to begin in April 2017.

Bancroft Elementary School

The construction mobilization started in February 2017 and the construction work is scheduled to begin in April 2017 with fire sprinkler system, perimeter access control system, and associated door hardware.

Beals Elementary School

Construction work on the new fire alarm system is scheduled to be complete in March 2017 and the demolition of the old fire alarm system is scheduled to be complete in April 2017.

Belle Ryan Elementary School

The structural steel erection work was complete in February 2017. The exterior metal stud framing is ongoing and is scheduled to be complete in April 2017. The concrete slab on deck work is ongoing and is scheduled to be complete in March 2017. The roof installation work is ongoing and is scheduled to be complete in April 2017.

Belvedere Elementary School

Construction of the fire alarm system has been completed with the cutover of the new system and demolition of the old system is in the closeout phase with punch list items being completed.

Benson High School

The Phase 1 interior building construction work is ongoing and is scheduled to be complete in May 2017.

Benson West Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Beveridge Magnet Middle School

The Phase 3 construction work started in March 2017 which consists of mechanical, electrical, and plumbing work. The 1st addition interior building construction work is ongoing and the 2nd addition mechanical, electrical, and plumbing work is ongoing. The exterior masonry work has started on the 1st and 2nd addition which is scheduled to be complete in June 2017.