All Bond News

rss

Bond News

Omaha Public Schools site for all news related to school bond projects.

Adams Elementary School

Construction work has started in January 2017 with the safe area addition. Fire sprinkler and access control work is scheduled to begin in February 2017.

Ashland Park-Robbins Elementary School

The Bid/Award phase is scheduled to begin in February 2017.

Bancroft Elementary School

The bid/award was approved by the Board of Education on January 23, 2017. Construction mobilization will begin in February 2017.

Beals Elementary School

The fire alarm system and perimeter access control system bid/award was approved by the Board of Education on December 12, 2016. Construction mobilization has started in January 2017.

Belle Ryan Elementary School

The footings and foundation walls were completed in December 2016. The plumbing and electrical underground work was completed in December 2016. The structural steel erection work started in December 2016 and will be ongoing through Winter 2017. The exterior metal stud framing is scheduled to begin work in January 2017.

Belvedere Elementary School

Construction of the fire alarm system is near completion and the closeout phase will begin in February 2017.

Benson High School

The GMP Amendment was approved by the Board of Education on January 23, 2017. Phase 1 interior demolition work started in January 2017.

Benson West Elementary School

Construction work has started in January 2017 with construction of the safe area. Fire sprinkler and access control work is scheduled to begin in February 2017.

Beveridge Magnet Middle School

Phase 3 abatement work is scheduled to be completed in January 2017 and the demolition work for Phase 3 is scheduled to begin in late January 2017. The steel construction work on the 1st addition was completed in December 2016. The 1st addition interior building construction work has started in January 2017. The 2nd addition exterior structural walls are in progress and will be closed and completed in February 2017.

Blackburn Alternative Program

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

OPS Bond Email Alerts Signup