Omaha Public Schools site for all news related to school bond projects.

32nd & Burt Street

The Schematic Design package was approved by the Board of Education on May 1, 2017. The project is currently in the Design Development phase which is scheduled to be complete in June 2017. The Construction Documents phase is scheduled to begin in July 2017.

Adams Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Ashland Park-Robbins Elementary School

The construction mobilization started in April 2017. The scope of work consists of fire alarm upgrades, door hardware replacement and access control system which will begin in June 2017.

Bancroft Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Beals Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Belle Ryan Elementary School

The interior metal stud framing and the mechanical, electrical and plumbing rough in work is ongoing and is scheduled to be complete in June 2017. The exterior masonry work on the building started in May 2017 and is scheduled to be complete in June 2017. The exterior insulation finish system is scheduled to start in June 2017 and is scheduled to be complete in August 2017.

Belvedere Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on April 3, 2017.

Benson High School

The Phase 1 interior building construction work is ongoing and is scheduled to be complete in May 2017. Phase 2 interior building construction work is scheduled to begin in June 2017 and is scheduled to be complete in August 2017. The GMP Amendment #002 for the temporary classroom portables construction work is going to the Board of Education for approval on June 5, 2017.

Benson West Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Beveridge Magnet Middle School

The Phase 3A construction renovation work was complete in May 2017 and is now occupied as classroom space. The Phase 3B construction renovation work is ongoing and is scheduled to be complete in July 2017. The 1st addition interior building construction work is ongoing and the 2nd addition mechanical, electrical, and plumbing work is ongoing. The exterior masonry work is complete on the 1st addition and 2nd addition masonry work is ongoing which is scheduled to be complete in June 2017.