Omaha Public Schools site for all news related to school bond projects.

32nd & Burt Street

The project is currently in the Design Development phase which is scheduled to be complete in June 2017. The Construction Documents phase is scheduled to begin in July 2017.

Adams Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Ashland Park-Robbins Elementary School

The construction work is in progress on the fire alarm upgrades, door hardware replacement and access control system.

Bancroft Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Beals Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Belle Ryan Elementary School

The interior metal stud framing and the mechanical, electrical and plumbing rough in work was complete in June 2017. The exterior masonry work on the building was complete in June 2017. The exterior insulation finish system is scheduled to start in June 2017 and is scheduled to be complete in August 2017. The interior drywall installation along with window installation started in June 2017 and is scheduled to be complete in August 2017.

Belvedere Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on April 3, 2017.

Benson High School

The Phase 1 interior building construction work was complete in May 2017. Phase 2 interior building construction work is ongoing and is scheduled to be complete in August 2017. The GMP Amendment #002 for the temporary classroom portables construction work was approved by the Board of Education on June 5, 2017.

Benson West Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Beveridge Magnet Middle School

The Phase 3B construction renovation work is ongoing and is scheduled to be complete in July 2017. The 1st addition interior building construction work is ongoing and the 2nd addition mechanical, electrical, and plumbing work is ongoing. The exterior masonry work on the 1st addition and 2nd addition was complete in June 2017. The construction work on the North student drop off area started in June 2017 and is scheduled to be complete in August 2017.