Omaha Public Schools site for all news related to school bond projects.

32nd & Burt Street

The site preparation package work started in August 2017 and is scheduled to be complete in October 2017. The Construction Documents are scheduled to go to the Board of Education for approval in October 2017. The next phase is the bid/award phase and that is scheduled to be complete in October 2017.

Adams Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on July 24, 2017.

Ashland Park-Robbins Elementary School

The construction work is in progress on the fire alarm upgrades, door hardware replacement and access control system.

Bancroft Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Beals Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.

Belle Ryan Elementary School

The exterior insulation finish system is ongoing and is scheduled to be complete in September 2017. The interior drywall installation along with window installation is ongoing and is scheduled to be complete in September 2017. The ceramic tile installation is ongoing and is scheduled to be complete in October 2017. The building interior finishes work started in September 2017 and is scheduled to be complete in November 2017. The office and classroom furniture is scheduled to be delivered and assembled in October 2017.

Belvedere Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on April 3, 2017.

Benson High School

The temporary classroom portables are set on the south side parking lot and are being utilized as classroom space for the 2017/2018 school year. The Phase 3 interior building construction work started in August 2017 and is scheduled to be complete in December 2017. The Phase 4 interior building construction work is scheduled to begin in January 2018.

Benson West Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on July 24, 2017.

Beveridge Magnet Middle School

The Phase 3B construction work is ongoing and is scheduled to be complete in November 2017. The 1st addition and 2nd addition interior building construction work is near completion with minor punch list work scheduled to be complete in September 2017. The construction work on the North student drop off area and courtyard area was complete in September 2017. The northwest cul-de-sac construction work is scheduled to be complete in October 2017.