Wilson Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

32nd & Burt Street

The Construction Documents phase started in July 2017 and is scheduled to be complete in August 2017. The next phase is the bid/award phase and that is scheduled to be complete in September 2017.

Adams Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on July 24, 2017.

Ashland Park-Robbins Elementary School

The construction work is in progress on the fire alarm upgrades, door hardware replacement and access control system.

Bancroft Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Beals Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Belle Ryan Elementary School

The exterior insulation finish system is ongoing and is scheduled to be complete in August 2017. The interior drywall installation along with window installation is ongoing and is scheduled to be complete in August 2017. The ceramic tile installation started in July 2017 and is scheduled to be complete in October 2017.

Belvedere Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on April 3, 2017.

Benson High School

The temporary classroom portables are set on the south side parking lot and are scheduled to be available for classroom space for the start of school in August 2017. The Phase 2 interior building construction work is ongoing and is scheduled to be complete in August 2017. The Phase 3 interior building construction work is scheduled to begin in Fall 2017.

Benson West Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on July 24, 2017.