Omaha Public Schools site for all news related to school bond projects.

Jefferson Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Joslyn Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. The substantial completion is scheduled to go to the Board of Education for approval in October 2017.

JP Lord Alternative Program

The exterior masonry work is ongoing and is scheduled to be complete in September 2017. The site parking lot and perimeter sidewalk construction work is scheduled to be complete in October 2017. The interior drywall and tile construction work is ongoing. The mechanical, electrical, and plumbing rough in work is ongoing. The therapy pool equipment package was delivered in September 2017 and the installation work is ongoing.

Kellom Elementary School

This project has not been started. The planned design phase start date is Spring 2018.

Kennedy Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

King Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on June 19, 2017.

King Science Middle School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017.

Lewis & Clark Middle School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Liberty Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Lothrop Magnet Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion is scheduled to be submitted for approval to the Board of Education in October 2017.