Omaha Public Schools site for all news related to school bond projects.

Franklin Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 7, 2017.

Fullerton Magnet Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Gilder Elementary School

The construction work on the seven (7) classroom, administration, and media center additions is ongoing. The masonry work for the storm shelter safe area was complete in September 2017. The mechanical, electrical and plumbing rough in work is ongoing in the storm shelter safe area and is scheduled to be complete in October 2017.

Gomez Heritage Elementary School

The scope of work is a video intercom system installation and the work has been completed.

Hale Middle School

The CM@R selection interviews are complete and the CM@R selection is scheduled to go to the Board of Education for approval on October 2, 2017. The Schematic Design package is scheduled to go to the Board of Education for approval in October 2017.

Harrison Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Hartman Elementary School

The Schematic Design package is scheduled to go to the Board of Education for approval in October 2017.

Highland Elementary School

The construction work is in progress on the fire sprinkler upgrades, door hardware replacement, access control system and storm safe area upgrades.

Indian Hill Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion is scheduled to be submitted for approval to the Board of Education in October 2017.

Jackson Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.