Franklin Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 7, 2017.

Fullerton Magnet Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Gilder Elementary School

The temporary portables construction work is complete and in use for classroom utilization. The construction work on the seven (7) classroom, administration, and media center additions is ongoing. The Phase 1 interior renovation work along with window installation and interior finishes was complete in August 2017.

Gomez Heritage Elementary School

The scope of work is a video intercom system installation and the work has been completed.

Hale Middle School

The Educational Specifications package was approved by the Board of Education on July 24, 2017. The project is now in the Schematic Design phase.

Harrison Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Hartman Elementary School

The Educational Specifications package was approved by the Board of Education on August 21, 2017. The project is now in the Schematic Design phase.

Highland Elementary School

The construction work is in progress on the fire sprinkler upgrades, door hardware replacement and access control system.

Indian Hill Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion is scheduled to be submitted for approval to the Board of Education in September 2017.

Jackson Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.