Omaha Public Schools site for all news related to school bond projects.

Hartman Elementary School

The design firm selection will be going to the Board of Education for approval on June 5, 2017.

Highland Elementary School

The construction mobilization started in April 2017. The scope of work consists of fire alarm upgrades, door hardware replacement and access control system which will begin in June 2017.

Indian Hill Elementary School

Phase 4 interior building renovations started in March 2017 and is scheduled to be complete in June 2017. Phase 5 interior building renovations are scheduled to start in June 2017 and is scheduled to be complete in August 2017.

Jackson Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Jefferson Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Joslyn Elementary School

The open to close and multipurpose interior renovation construction work is ongoing and is scheduled to be complete in July 2017.

JP Lord Alternative Program

The structural steel work is ongoing and is scheduled to be complete in June 2017. The exterior masonry work is ongoing and is scheduled to be complete in August 2017. The concrete floor slab construction work is ongoing and is scheduled to be complete in July 2017.

Kellom Elementary School

This project has not been started. The planned design phase start date is Spring 2018.

Kennedy Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

King Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.