Omaha Public Schools site for all news related to school bond projects.

Edison Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on December 12, 2016.

Field Club Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Florence Elementary School

The capital improvements at this site have been scheduled to be constructed during the 2017-2018 school year to coincide with the Boys and Girls Club addition. The school will be temporarily housed at the Mills Building during the construction phase in 2017-2018. The ground breaking ceremony took place in May 2017 and the construction mobilization will begin in late May 2017.

Fontenelle Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Franklin Elementary School

The School has been relocated to the Mills Building for the 2016-2017 District school year. The open to close classroom walls are installed and painting is in progress. The carpeting of the School will begin in May 2017 and is scheduled to be complete in June 2017. The building entry, sidewalks, and ramp is scheduled to be complete in June 2017.

Fullerton Magnet Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Gilder Elementary School

The temporary portables construction work has started in May 2017 and is scheduled to be complete in July 2017. The interior renovation construction work is scheduled to begin in June 2017. The construction work on the seven (7) classroom, administration, and media center additions will begin in June 2017.

Gomez Heritage Elementary School

The scope of work is a video intercom system installation and the work has been completed.

Hale Middle School

The design firm selection was approved by the Board of Education on May 1, 2017 with the award going to Kenneth Hahn Architects. The project is currently in the Educational Specifications phase.

Harrison Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.