All Bond News

rss

Bond News

Omaha Public Schools site for all news related to school bond projects.

Catlin Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on December 12, 2016.

Central High School

The construction work is ongoing with exterior masonry restoration, access control, and door hardware modifications work being performed. The fire alarm system reached substantial completion in January 2017. The access control system along with the door hardware modifications are scheduled to be complete in May 2017.

Central Park Elementary School

The construction work on the fire sprinkler system is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work has started in May 2017 and this work is scheduled to be complete in July 2017.

Chandler View Elementary School

Construction work on the new fire alarm system is ongoing and is scheduled to be complete in May 2017 and the demolition of the old fire alarm system is scheduled to be complete in June 2017. Data cabling upgrades are ongoing and are scheduled to be complete in July 2017.

Columbian Elementary School

The project is currently in the Educational Specifications phase which is scheduled to be complete in June 2017. The Schematic Design phase is scheduled to begin in June 2017.

Conestoga Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Crestridge Magnet Elementary School

The interior renovation construction work for Phase D is in progress and scheduled to be complete in July 2017. The administration office renovation will start in May 2017. The overall project substantial completion is scheduled to be complete in July 2017.

Dodge Elementary School

The Design Firm selection was approved by the Board of Education on April 3, 2017. The Educational Specifications phase started in April 2017.

Druid Hill Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Dundee Elementary School

The construction work on the fire sprinkler system is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work has started in May 2017 and this work is scheduled to be complete in July 2017.