Belvedere Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on April 3, 2017.

Benson High School

The Phase 1 interior building construction work is ongoing and is scheduled to be complete in May 2017. Phase 2 interior building construction work is scheduled to begin in June 2017 and is scheduled to be complete in August 2017. The GMP Amendment #002 for the temporary classroom portables construction work is going to the Board of Education for approval on June 5, 2017.

Benson West Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Beveridge Magnet Middle School

The Phase 3A construction renovation work was complete in May 2017 and is now occupied as classroom space. The Phase 3B construction renovation work is ongoing and is scheduled to be complete in July 2017. The 1st addition interior building construction work is ongoing and the 2nd addition mechanical, electrical, and plumbing work is ongoing. The exterior masonry work is complete on the 1st addition and 2nd addition masonry work is ongoing which is scheduled to be complete in June 2017.

Blackburn Alternative Program

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS. The generator project was bid/award in May 2017 and the construction mobilization for that work will begin in June 2017 with work scheduled to be complete in August 2017.

Boyd Elementary School

The Design Firm selection was approved by the Board of Education on April 3, 2017. The Educational Specifications phase started in April 2017.

Bryan High School

The Educational Specifications phase is ongoing with design meetings scheduled in May and June 2017.

Bryan Middle School

The design firm selection was approved by the Board of Education on May 1, 2017 with the award going to Holland Basham Architects. The project is currently in the Educational Specifications phase.

Burke High School

The temporary portables construction work is complete. The Phase 1 interior building construction work in the cafeteria is ongoing and is scheduled to be complete in August 2017. The new fire sprinkler system, new doors and door hardware, and interior painting is scheduled to begin in June 2017. The new multipurpose room located on the west side of the school is scheduled to begin construction work in June 2017.

Castelar Elementary School

Construction work on the new fire alarm system is ongoing and is scheduled to be complete in May 2017 and the demolition of the old fire alarm system is scheduled to be complete in June 2017. Data cabling upgrades are ongoing and are scheduled to be complete in July 2017.