Saddlebrook Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Saratoga Elementary School

The School will be renovated to serve the ILP (Integrated Learning Program). The scope of work consists of remodeling classrooms to serve K-12 students. The construction work started in June 2017 and substantial completion is scheduled at the end of July 2017.

Sherman Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Skinner Elementary School

The construction work on the classroom door hardware is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work has started in May 2017 and this work is scheduled to be complete in July 2017.

South High School

The project is currently in the closeout phase with punch list items being finalized.

Spring Lake Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Springville Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Standing Bear Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Sunny Slope Elementary School

The interior construction work on the new addition is ongoing with interior finishes and site work. The new addition is scheduled to be complete in July 2017.

Wakonda Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.