Omaha Public Schools site for all news related to school bond projects.

Mount View Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Norris Middle School

The Phase 1 interior work is ongoing and is scheduled to be complete in August 2017. The construction work for Bid Package #02 which consists of site, steel and foundation work is ongoing. The final GMP Amendment #003 that contains mechanical, electrical, plumbing, interior and exterior building work was approved by the Board of Education on June 19, 2017.

North High School

Substantial completion was approved by the Board of Education on April 4, 2016. Project closeout documents have been submitted and transmitted to OPS.

Northwest Magnet High School

The construction work for the new gymnasium addition is ongoing along with the interior building renovation. Interior finish work is being done on the new administrative addition and the new addition is scheduled to be complete in June 2017.

Oak Valley Elementary School

The demolition construction work is ongoing and is scheduled to be complete in July 2017. The new addition building footings construction work started in June 2017. The temporary classroom portables construction work started in June 2017 and is scheduled to be complete in July 2017. The three (3) temporary classroom portables are being relocated from Crestridge Elementary School.

Pawnee Elementary School

The construction work is in progress on the fire sprinkler upgrades, door hardware replacement, access control system, and new storm safe area.

Picotte Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Ponca Elementary School

The construction work is complete and the closeout phase is near completion with project closeout documents being transmitted and submitted to OPS. Substantial completion was approved by the Board of Education on March 21, 2016. The District held a ribbon cutting ceremony at the school on August 16, 2016.

Prairie Wind Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Rose Hill Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.