Highland Elementary School

The construction work is in progress on the fire sprinkler upgrades, door hardware replacement and access control system.

Indian Hill Elementary School

The Phase 4 interior building renovations were complete in June 2017. The Phase 5 interior building renovations work started in June 2017 and is scheduled to be complete in August 2017.

Jackson Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Jefferson Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Joslyn Elementary School

The open to close and multipurpose interior renovation construction work is ongoing and is scheduled to be complete in August 2017.

JP Lord Alternative Program

The structural steel work was complete in June 2017. The roof membrane installation is complete and the final roofing items will be complete in late June 2017. The mechanical, electrical, and plumbing rough in work is ongoing. The interior metal framing has started in June 2017. The concrete floor slab construction work is ongoing and is scheduled to be complete in July 2017. The exterior masonry work is ongoing and is scheduled to be complete in August 2017.

Kellom Elementary School

This project has not been started. The planned design phase start date is Spring 2018.

Kennedy Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

King Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on June 19, 2017.

King Science Middle School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017.