Washington Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Western Hills Magnet Elementary School

The exterior insulation finish system is ongoing and is scheduled to be complete in September 2017. The interior drywall installation is ongoing and is scheduled to be complete in August 2017. Site grading and site concrete paving started in July 2017 and is scheduled to be complete in September 2017. The window installation construction work is scheduled to begin in August 2017.

Wilson Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

32nd & Burt Street

The project is currently in the Design Development phase which is scheduled to be complete in June 2017. The Construction Documents phase is scheduled to begin in July 2017.

Adams Elementary School

Construction work is ongoing in the safe area addition, the fire sprinkler system, and access control system.

Ashland Park-Robbins Elementary School

The construction work is in progress on the fire alarm upgrades, door hardware replacement and access control system.

Bancroft Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Beals Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items.

Belle Ryan Elementary School

The interior metal stud framing and the mechanical, electrical and plumbing rough in work was complete in June 2017. The exterior masonry work on the building was complete in June 2017. The exterior insulation finish system is scheduled to start in June 2017 and is scheduled to be complete in August 2017. The interior drywall installation along with window installation started in June 2017 and is scheduled to be complete in August 2017.

Belvedere Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on April 3, 2017.