All Bond News

rss

Bond News

Omaha Public Schools site for all news related to school bond projects.

Norris Middle School

The Phase 1 and 2 interior construction work is ongoing and is scheduled to be complete in August 2017. The Phase 3 interior construction work has started in July 2017 and is scheduled to be complete in December 2017.

North High School

Substantial completion was approved by the Board of Education on April 4, 2016. Project closeout documents have been submitted and transmitted to OPS.

Northwest Magnet High School

The construction work for the new gymnasium addition is ongoing along with the interior building renovations. Interior finish work is being finalized on the new administrative addition which is scheduled to be substantially complete in July 2017.

Oak Valley Elementary School

The Phase 1, 2, 3, and 4 demolition construction was complete in July 2017. The new addition building footings construction work was complete in July 2017. The steel is on site and the steel erection is scheduled to start in August 2017. The three (3) temporary classroom portables have been relocated from Crestridge Elementary School. The temporary classroom portables construction work is ongoing and is scheduled to be complete in July 2017.

Pawnee Elementary School

The construction work is in progress on the fire sprinkler upgrades, access control system, and new storm safe area.

Picotte Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Ponca Elementary School

The construction work is complete and the closeout phase is near completion with project closeout documents being transmitted and submitted to OPS. Substantial completion was approved by the Board of Education on March 21, 2016. The District held a ribbon cutting ceremony at the school on August 16, 2016.

Prairie Wind Elementary School

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS.

Rose Hill Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Saddlebrook Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.