Crestridge

Crestridge is currently in the Schematic Design phase of the project which is currently scheduled to be submitted to the Board of Education for approval on August 3, 2015.

Dundee

The Architectural selection process has been completed for Planning Area B schools ( Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform design services for this project. Estimated Schematic Design Date October 12th. Bid date estimated first part of December 2015.

Edison

Construction Bid Date happened June 2, 2015. Package 1 (Fullerton, Picotte, Prairie Wind), bids were received and recommending Midwest DCM to the Board on June 15. Package 2 (Catlin, Edison, Masters), no bids were received. Package 2 will be bid in late fall, construction to begin in Spring 2016.

Florence

Educational Specifications are currently in progress. Educational Specifications are scheduled to be sent to the Board of Education on August 3.

Franklin

The final Education Specification Committee meeting with Architect was held on June 22nd. The Schematic Design will be presented to the BOE for approval on August 3rd, 2015.

Fullerton

Construction Bid Date happened June 2, 2015. Package 1 (Fullerton, Picotte, Prairie Wind). A preconstruction meeting was held with Midwest DCM on June 25.

Gomez

The scope of work is a video intercom installation. Contract purchase order has been issued to Miller Electric. The Work is scheduled to be completed Summer 2015.

Indian Hill

Indian Hill is in the Design Development phase of the project as the Schematic Design was approved by the Board of Education on August 3, 2015. Lund Ross Constructors was approved to be the CM At Risk contractor at the Board of Education meeting on August 3, 2015.

Joslyn

Educational Specifications were approved by the Board of Education on June 15, 2015. The project is currently in Schematic Design phase and is on schedule to present to BOE in September. .

King

The Architectural selection process has been completed for Planning Area B schools ( Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform design services for this project. Estimated Schematic Design Date October 12th. Bid date estimated first part of December 2015.