Omaha Public Schools site for all news related to school bond projects.

Northwest

Northwest High School is currently in the Schematic Design phase of the project which is scheduled to be submitted to the Board of Education during the first meeting in September 2015.

South

The Architectural selection process has been completed for South High School. Carlson West Povondra Architects has been selected to perform design services for this project.

Blackburn

Construction is ongoing. Demolition is complete and Fire Sprinkler is currently being installed.

JP Lord

The top 3 A/E Firms were interviewed on July 9th with BCDM selected to design the school. The BOE recommendation to contract with BCDM is on the July 20th agenda.

Adams Elementary School

The Architectural selection process has been completed for Planning Area B schools ( Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform design services for this project. Estimated Schematic Design Date October 12th. Bid date estimated first part of December 2015.

Belle Ryan

The Educational Specifications Submittal was approved June 1, 2015. Schematic Design Submittal expected to be complete mid to late August. Forecasted cost projection is (Over) budget due to demolition costs, site development costs, additional space programing requirements for new building, and cost per square foot differential. Sampson Construction was approved to be the CM At Risk contractor July 6, 2015.

Benson West

The Architectural selection process has been completed for Planning Area B schools ( Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform design services for this project. Estimated Schematic Design Date October 12th. Bid date estimated first part of December 2015.

Catlin

Construction Bid Date happened June 2, 2015. Package 1 (Fullerton, Picotte, Prairie Wind), bids were received and recommending Midwest DCM to the Board on June 15. Package 2 (Catlin, Edison, Masters), no bids were received. Package 2 will be bid in late fall and construction is scheduled to start spring of 2016.

Central Park

The Architectural selection process has been completed for Planning Area B schools ( Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform design services for this project. Estimated Schematic Design Date October 12th. Bid date estimated first part of December 2015.

Conestoga

The Architectural selection process has been completed for Planning Area B schools ( Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform design services for this project. Estimated Schematic Design Date October 12th. Bid date estimated first part of December 2015.