Omaha Public Schools site for all news related to school bond projects.

Wakonda

The Bond Scope of Work is limited to video intercom. The Work is scheduled to be completed by the District in August 2015. This project will be closed out after District completion.

Western Hills

The Educational Specifications Submittal was approved June 1, 2015. Schematic Design Submittal expected to be complete mid to late August. Forecasted cost projection is (Over) budget due to demolition costs, site development costs, additional space programing requirements for new building, and cost per square foot differential. Sampson Construction was approved to be the CM At Risk contractor July 6, 2015.

Beveridge

Ed Spec meetings have begun and will finish in mid August. CMR selection will be in early August.

Lewis & Clark

Mark VII started construction on May 26th. Construction continues with the installation of the Fire Alarm and Sprinkler systems. The new water main for the Fire Sprinkler system has been installed and completed to the building.

Marrs

Downs Electric Inc. was selected as the Contractor. Construction is currently underway.

McMillan

The scope of work is limited to card access. The initial program budget is not sufficient however the additional funds required are available within the bid pack (Lewis and Clark, Monroe and McMillian Middle Schools FLSS). Project scope is currently in design.

Monroe

The scope of work is limited to card access. The initial program budget is not sufficient however the additional funds required are available within the bid pack (Lewis and Clark, Monroe and McMillian Middle Schools FLSS). Project scope is currently in design.

Morton

Midwest DCM started construction on May 26th. Construction continues with the installation of the Fire Alarm, Fire Sprinkler systems, and door access control system.

Central

The Architectural selection process has been completed for Central High School. Alley Poyner Machietto has been selected to perform design services for this project. Jacobs and Alley Poyner have met with the Central High School Foundation to coordinate exterior work with a planned exterior plaza by the foundation scheduled for 2016.

North

Project bid was completed on June 2nd and the Construction phase came in under budget. Notice of Contract Award was issued on June 9th to Elkhorn West. A pre-construction meeting was held on July 7th and the General Contractor's work schedule is scheduled to be submitted on July 17th. The first OAC meeting is scheduled to be held on July 21st.