Marrs Middle School

Construction technology is currently in progress with data cable installation throughout the school. This work is scheduled to be complete by the end of December 2015.

Masters Elementary School

Area C bid package 2 (Catlin, Edison, Masters) is scheduled to bid in late Fall 2015. The construction phase is scheduled to start in Spring 2016.

McMillan Middle School

The scope of work is limited to card access. The initial program budget is not sufficient; however, the additional funds required are available within the bid package (Lewis and Clark, Monroe and McMillian Middle Schools FLSS). Project scope is currently in the design phase.

Monroe Middle School

The scope of work is limited to card access. The initial program budget is not sufficient; however, the additional funds required are available within the bid package (Lewis and Clark, Monroe and McMillian Middle Schools FLSS). Project scope is currently in the design phase.

Morton Middle School

Construction continues with the installation of the fire alarm system, fire sprinkler system, and door access control system.

Mount View Elementary School

The Bond Scope of Work is limited to video intercom. The Work is scheduled to be complete by December 31, 2015.

North High School

Construction is in progress with installation of the card access system.

Northwest High School

The project is currently in the Schematic Design phase. The final Schematic Design documents will be presented to the Board of Education in September 2015.

Picotte Elementary School

The new fire main line has been installed. Electrical construction work has started on the fire alarm system and the card access system is ongoing. The fire sprinkler work is ongoing.

Ponca Elementary School

Construction has started in the main building. Current activities include demolition of various building components, interior HVAC installation, fire alarm installation, and miscellaneous site work activities.