Omaha Public Schools site for all news related to school bond projects.

Benson West Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in the first part of December 2015.

Beveridge Middle School

Educational Specification meetings are continuing and are anticipated to be complete in September 2015. The CM At Risk selection is currently underway with CM At Risk interviews scheduled for August 25th, 2015.

Blackburn Alternative School

Construction is 95% complete. Rife Construction to start after hours work beginning on August 12th, 2015.

Catlin Elementary School

Area C bid package 2 (Catlin, Edison, Masters) is scheduled to bid in late Fall 2015. The construction phase is scheduled to start in Spring 2016.

Central High School

The project is currently in the Schematic Design phase. The design team is performing on site field visits to verify existing conditions and create detailed project scope items.

Central Park Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in the first part of December 2015.

Conestoga Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in the first part of December 2015.

Crestridge Elementary School

Crestridge is currently in the Schematic Design phase. The Schematic Design documents will be presented to the Board of Education in September 2015.

Dundee Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in the first part of December 2015.

Edison Elementary School

Area C bid package 2 (Catlin, Edison, Masters) is scheduled to bid in late Fall 2015. The construction phase is scheduled to start in Spring 2016.