Omaha Public Schools site for all news related to school bond projects.

Blackburn Alternative Program

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS. The generator project construction work along with IT equipment installation is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion is scheduled to go to the Board of Education for approval in October 2017.

Boyd Elementary School

The Schematic Design package is scheduled to go to the Board of Education for approval in October 2017.

Bryan High School

The CM@R interview selection was approved by the Board of Education on August 21, 2017. The project is currently in the Design Development phase.

Bryan Middle School

The CM@R interview selection was approved by the Board of Education on August 21, 2017. The project is currently in the Design Development phase.

Burke High School

The new multipurpose room addition construction work is ongoing with concrete footings, masonry and steel erection. Site concrete work located on the East side of the building was complete in August 2017.

Castelar Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.

Catlin Elementary School

Substantial completion was approved by the Board of Education on December 12, 2016. Project closeout documents have been submitted and transmitted to OPS.

Central High School

The fire, life safety and security work is substantially complete and is in the closeout phase. The exterior masonry restoration work is ongoing and is scheduled to be complete in November 2017.

Central Park Elementary School

The construction work on the fire sprinkler system is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work is complete and the contractor is in the closeout phase which involves punch list items.

Chandler View Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.