Omaha Public Schools site for all news related to school bond projects.

Blackburn Alternative Program

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS. The generator project construction work along with IT equipment installation is ongoing with work scheduled to be complete in August 2017.

Boyd Elementary School

The Educational Specifications package was approved by the Board of Education on July 24, 2017. The project is now in the Schematic Design phase.

Bryan High School

The Schematic Design package was approved by the Board of Education on August 21, 2017. The CM@R interview selection was approved by the Board of Education on August 21, 2017. The project is currently in the Design Development phase.

Bryan Middle School

The Schematic Design package was approved by the Board of Education on August 21, 2017. The CM@R interview selection was approved by the Board of Education on August 21, 2017. The project is currently in the Design Development phase.

Burke High School

The Phase 1 interior building construction work in the cafeteria was complete in August 2017. The new multipurpose room construction is ongoing with concrete footings and exterior masonry work. Site concrete work located on the East side of the building is scheduled to be complete in August 2017.

Castelar Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.

Catlin Elementary School

Substantial completion was approved by the Board of Education on December 12, 2016. Project closeout documents have been submitted and transmitted to OPS.

Central High School

The fire alarm system reached substantial completion in January 2017. The access control system along with the door hardware modifications was complete in July 2017. The construction work is ongoing with exterior masonry restoration work and is scheduled to be complete in November 2017.

Central Park Elementary School

The construction work on the fire sprinkler system is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work is complete and the contractor is in the closeout phase which involves punch list items.

Chandler View Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on August 21, 2017.