Omaha Public Schools site for all news related to school bond projects.

New South Elementary School Area #1

The District is in the land procurement phase and is actively pursuing land acquisition.

New South Elementary School Area #2

The District is in the land procurement phase and is actively pursuing land acquisition.

New South High School

Property acquisition approved by Board of Education on June 16, 2015 at property 5602 and 5616 L Street. The land purchase transaction was executed on September 9, 2015 for an amount of $5.73 million.

New West High School

Potential land acquisition has been identified for seven (7) properties located around 156th and Ida Streets. The Board of Education approved The Lund Company to be the real estate broker to help negotiate the purchase of three (3) properties located around 156th and Ida Streets. A public hearing pursuant to Nebraska Revised Statutes sections 79-1096 and 25-2504 will take place for the property owners whose land is being negotiated for purchase.

Norris Middle School

This project has not been started. The planned design phase start date is January 2016.

North High School

Construction is in progress with installation of the card access system.

Northwest Magnet High School

The project is currently in the Schematic Design phase. The final Schematic Design documents will be presented to the Board of Education in October 2015. The selection process for a CM At Risk contractor has commenced with an anticipated Board of Education recommendation date of October 5, 2015.

Oak Valley Elementary School

This project has not been started. The planned design phase start date is February 2016.

Pawnee Elementary School

This project has not been started. The planned design phase start date is October 2015.

Picotte Elementary School

The new fire main line has been installed. Electrical construction work has started on the fire alarm system and the card access system is ongoing. The fire sprinkler work is ongoing.