Indian Hill Elementary School

Indian Hill is in the Design Development phase. The Schematic Design was approved by the Board of Education on August 3, 2015. Lund Ross Constructors was approved to be the CM At Risk contractor at the Board of Education meeting on August 3, 2015.

Jackson Elementary School

This project has not been started. The planned design phase start date is October 2015.

Jefferson Elementary School

This project has not been started. The planned design phase start date is October 2015.

Joslyn Elementary School

The project is currently in Schematic Design review phase and will be submitted to the Board of Education for approval in October 2015.

JP Lord Alternative Program

The Educational Specification Committee meetings are underway; the meetings were held on August 27, 2015 and September 10, 2015. The Committee and BCDM Architects presented project information and solicited information from both parents and staff at the J. P. Lord Back to School Night on September 3, 2015.

Kellom Elementary School

This project has not been started. The planned design phase start date is May 2018.

Kennedy Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

King Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in March 2016.

King Science Middle School

The scope of work consists of perimeter access (card access) control and will be completed August 2016.

Lewis & Clark Middle School

Construction continues with the installation of the fire alarm and sprinkler systems. The new water main line for the fire sprinkler system has been installed.