Omaha Public Schools site for all news related to school bond projects.

Florence Elementary School

The Schematic Design submittal is to be completed by October 2015.

Fontenelle Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Franklin Elementary School

The Educational Specification document was approved by the Board of Education on August 3rd, 2015. The Schematic Design submittal is to be completed by September 2015.

Fullerton Magnet Elementary School

Electrical construction work has started on the fire alarm system and the card access system is ongoing.

Gilder Elementary School

This project has not been started. The planned design phase start date is February 2017.

Gomez Heritage Elementary School

The scope of work is a video intercom system installation and the work has been completed by Miller Electric.

Hale Middle School

This project has not been started. The planned design phase start date is February 2017.

Harrison Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Hartman Elementary School

This project has not been started. The planned design phase start date is August 2017.

Highland Elementary School

This project has not been started. The planned design phase start date is October 2015.