Omaha Public Schools site for all news related to school bond projects.

Central Park Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in March 2016.

Chandler View Elementary School

This project has not been started. The planned design phase start date is October 2015.

Columbian Elementary School

This project has not been started. The planned design phase start date is January 2017.

Conestoga Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in March 2016.

Crestridge Magnet Elementary School

The project is currently in the Schematic Design phase. The Schematic Design documents will be presented to the Board of Education in October 2015.

Dodge Elementary School

This project has not been started. The planned design phase start date is February 2017.

Druid Hill Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Dundee Elementary School

The Architectural selection process has been completed for Planning Area B schools (Adams, Benson West, Central Park, Conestoga, Dundee, King, and Skinner). Carlson West Povondra Architects has been selected to perform Design Services. The Schematic Design submittal will be completed in October 2015 and the bid date will take place in March 2016.

Edison Elementary School

Area C bid package 2 (Catlin, Edison, Masters) is scheduled to bid in late Fall 2015. The construction phase is scheduled to start in Spring 2016.

Field Club Elementary School

This project has not been started. The planned design phase start date is October 2015.