All Bond News

rss

Bond News

Omaha Public Schools site for all news related to school bond projects.

Bancroft Elementary School

This project has not been started. The planned design phase start date is October 2015.

Beals Elementary School

This project has not been started. The planned design phase start date is October 2015.

Belle Ryan Elementary School

The Schematic Design submittal is to be completed by the beginning of October 2015. Swing space options are being reviewed and evaluated at this time. Forecasted cost projection is (Over) budget due to demolition costs, site development costs, additional space programing requirements for new building, and cost per square foot differential.

Belvedere Elementary School

The scope of work consists of fire alarm upgrades and video intercom system at main entry.

Benson High School

This project has not been started. The planned design phase start date is January 2016.

Beveridge Magnet Middle School

Educational Specification meetings are continuing and are anticipated to be complete in September 2015. McCarthy Building Companies was selected as the CM At Risk contractor which was approved by the Board of Education on September 9, 2015.

Blackburn Alternative Program

Construction is 95% complete. Rife Construction to start after hours work beginning on August 12, 2015.

Boyd Elementary School

This project has not been started. The planned design phase start date is February 2017.

Bryan Middle School

This project has not been started. The planned design phase start date is February 2017.

Central High School

The project is currently in the Schematic Design phase. The design team is performing on site field visits to verify existing conditions and create detailed project scope items.