Omaha Public Schools site for all news related to school bond projects.

North High School

Construction work is currently in progress with the doors & hardware replacements being installed. The framing of interior walls with openings in corridors and the finish work along with the access control system is being completed throughout the building.

Northwest Magnet High School

Vrana Construction was selected as the CM At Risk contractor which was approved by the Board of Education on October 5, 2015. The project is currently in the Schematic Design phase. OPS, Jacobs, KAI and Vrana will be meeting with the community and Educational Specification committee in October 2015 to provide an update regarding the key design elements of the project.

Oak Valley Elementary School

This project has not been started. The planned design phase start date is February 2016.

Pawnee Elementary School

The Architectural selection process has been completed for Planning Area A schools. Alvine Engineering has been selected to perform Design Services.

Picotte Elementary School

The new fire main line has been installed. Electrical construction work has started on the fire alarm system and the card access system is ongoing. The fire sprinkler work is ongoing.

Ponca Elementary School

Construction work continues to progress. Structural steel has been erected at the 'Safe Area', main entry lobby, and secured entrance. Concrete Masonry Units (CMU) are being set in place in the Library. Various mechanical, electrical, and plumbing rough-in activities have been completed. Interior metal stud framing is continuing along with the setting of framework for the new windows. As part of Phase 1B, the gymnasium will be complete and ready for selective use by the school on October 26, 2015. The remaining areas of Phase 1 will be completed by November 2015.

Prairie Wind Elementary School

The new fire main line has been installed. Electrical construction work has started on the fire alarm system and the card access system is ongoing. The fire sprinkler work is ongoing.

Rose Hill Elementary School

The scope of work consisted of video intercom at the main entry and has been completed.

Saddlebrook Elementary School

The scope of work consists of video intercom. This project will be closed out after completion in Fall 2015.

Saratoga Elementary School

The scope of work consists of video intercom. The work is scheduled to be complete by December 2015.