Chandler View Elementary School

Construction work is complete on the new fire alarm system and the demolition of the old fire alarm system was complete in June 2017. Data cabling upgrades are ongoing and are scheduled to be complete in July 2017.

Columbian Elementary School

The Educational Specifications package was approved by the Board of Education on June 19, 2017. The project is now in the Schematic Design phase.

Conestoga Elementary School

The construction work is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on June 19, 2017.

Crestridge Magnet Elementary School

The interior renovation construction work for Phase D was complete in June 2017. The administration office renovation work is near completion and is scheduled to be complete in July 2017. The overall project substantial completion is scheduled for July 2017.

Dodge Elementary School

The Educational Specifications package is scheduled to go to the Board of Education for approval in August 2017.

Druid Hill Elementary School

Jacobs is working with the District staff to identify fire, life safety, security & technology scope of work items to be completed.

Dundee Elementary School

The construction work on the fire sprinkler system is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion was approved by the Board of Education on May 15, 2017. The access control system construction work is complete and the contractor is in the closeout phase which involves punch list items.

Edison Elementary School

Substantial completion was approved by the Board of Education on December 12, 2016. Project closeout documents have been submitted and transmitted to OPS.

Field Club Elementary School

The construction work is ongoing with fire sprinkler system, perimeter access control system, and associated door hardware replacement work.

Florence Elementary School

The school relocation to the Mills Building during the construction phase in 2017-2018 was complete in July 2017. The site construction work is ongoing and the interior abatement work started in July 2017 and is scheduled to be complete in September 2017.