Bond Update - April 6th, 2015

Current Major Activities Update
Received Construction Manager at Risk Statement of Qualification (SOQ) and Proposals for Ponca Elementary School, evaluation of SOQs and Proposals will occur next.     
Quickstart Projects - Construction bids for Marrs, Blackburn, Picotte, Prairie Wind and Fullerton (Planning Area C Package 1) are scheduled to be received on April 14 and 16, 2015.
Group 1 Projects* - Educational Specifications Committee meetings continue.  Negotiation of Architect Agreements on-going.   
Group 2 Projects** - Educational Specifications Committee meetings continue.  Negotiation of Architect Agreements on-going. 
Economic Inclusion - Meeting with construction contractors that have shown interest in bidding on 2014 Bond construction projects.     
 
*Group 1 Projects:
Capital Improvements – Northwest High School, Crestridge and Indian Hill Elementary Schools 
‘Open Plan’ Schools – Franklin and Sunny Slope Elementary Schools 
Replacement Schools – Belle Ryan and Western Hills Elementary Schools
 
**Group 2 Projects:
Capital Improvements – Florence Elementary School
‘Open Plan’ Schools – Lothrop and Joslyn Elementary Schools