Current Major Activities Update
Conducted Ponca Elementary pre-proposal meeting for Construction Manager at-Risk vendors to provide a site tour and answer any project specific questions.
Quickstart Projects - Marrs, Blackburn, Picotte, Prairie Wind and Fullerton (Planning Area C Package 1) advertisements for construction bids have been issued.
Group 1 Projects* - Educational Specifications Committee meetings continue.  Negotiation of Architect Agreements on-going.
Group 2 Projects** - Recommendation for Award of Design Services was approved at the March 16, 2015, Board of Education Meeting.
Economic Inclusion – Met with several community resources and contractors to encourage bidder participation in the Quickstart projects currently being advertised for construction bids.

*Group 1 Projects
Capital Improvements - Northwest High School, Crestridge and Indian Hill Elementary Schools '
Open Plan' Schools
- Franklin and Sunny Slope Elementary Schools
Replacement Schools - Belle Ryan and Western Hills Elementary Schools

**Group 2 Projects:
Capital Improvements - Florence Elementary School
'Open Plan' Schools- Lothrop and Joslyn Elementary Schools