JP Lord Alternative Program

The exterior masonry work is ongoing and is scheduled to be complete in September 2017. The site parking lot and perimeter sidewalk construction work is scheduled to be complete in October 2017. The interior drywall and tile construction work is ongoing. The mechanical, electrical, and plumbing rough in work is ongoing. The therapy pool equipment package was delivered in September 2017 and the installation work is ongoing.