Blackburn Alternative Program

Substantial completion was approved by the Board of Education on February 1, 2016. Project closeout documents have been submitted and transmitted to OPS. The generator project construction work along with IT equipment installation is complete and the contractor is in the closeout phase which involves punch list items. Substantial completion is scheduled to go to the Board of Education for approval in October 2017.