Beveridge Magnet Middle School

The Phase 3B construction work is ongoing and is scheduled to be complete in November 2017. The 1st addition and 2nd addition interior building construction work is near completion with minor punch list work scheduled to be complete in September 2017. The construction work on the North student drop off area and courtyard area was complete in September 2017. The northwest cul-de-sac construction work is scheduled to be complete in October 2017.