32nd & Burt Street

The site preparation package work started in August 2017 and is scheduled to be complete in October 2017. The Construction Documents are scheduled to go to the Board of Education for approval in October 2017. The next phase is the bid/award phase and that is scheduled to be complete in October 2017.