Western Hills Magnet Elementary School

The interior drywall installation is ongoing and is scheduled to be complete in August 2017. Site grading and site concrete paving is ongoing and is scheduled to be complete in September 2017. The window installation construction work started in August 2017 and is scheduled to be complete in October 2017. The interior finish construction work started in August 2017 and is scheduled to be complete in November 2017.