Western Hills Magnet Elementary School

The exterior insulation finish system is ongoing and is scheduled to be complete in September 2017. The interior drywall installation is ongoing and is scheduled to be complete in August 2017. Site grading and site concrete paving started in July 2017 and is scheduled to be complete in September 2017. The window installation construction work is scheduled to begin in August 2017.