Omaha Public Schools site for all news related to school bond projects.

Bryan Middle School

The Educational Specifications package was approved by the Board of Education on July 10, 2017. The project is currently in the Schematic Design phase. The CM@R proposals were received by the District in July 2017 and the CM@R interviews are scheduled to occur in August 2017. The restroom renovation construction work is near completion and is scheduled to be substantially complete in July 2017.