JP Lord Alternative Program

The structural steel work was complete in June 2017. The roof membrane installation is complete and the final roofing items will be complete in late June 2017. The mechanical, electrical, and plumbing rough in work is ongoing. The interior metal framing has started in June 2017. The concrete floor slab construction work is ongoing and is scheduled to be complete in July 2017. The exterior masonry work is ongoing and is scheduled to be complete in August 2017.