Beveridge Magnet Middle School

The Phase 3B construction renovation work is ongoing and is scheduled to be complete in July 2017. The 1st addition interior building construction work is ongoing and the 2nd addition mechanical, electrical, and plumbing work is ongoing. The exterior masonry work on the 1st addition and 2nd addition was complete in June 2017. The construction work on the North student drop off area started in June 2017 and is scheduled to be complete in August 2017.