Belle Ryan Elementary School

The interior metal stud framing and the mechanical, electrical and plumbing rough in work was complete in June 2017. The exterior masonry work on the building was complete in June 2017. The exterior insulation finish system is scheduled to start in June 2017 and is scheduled to be complete in August 2017. The interior drywall installation along with window installation started in June 2017 and is scheduled to be complete in August 2017.