Bond Update - June 2, 2015

Bond Update - June 2, 2015
Quick Start Projects:
Several projects have been bid out and on-site construction activities have commenced.
Ponca Elementary School will be issued for bid on June 08, 2015.

Group 1 Projects:
All Educational Specification packages are scheduled to be presented to the Board of Education during the month of June.
Group 2 Projects:
Architectural Selection for JP Lord will be completed in June 2015 with a recommendation presented to the Board of Education in July 2015.
Educational Specification is on-going at Florence, Joslyn and Lothrop.

Group 3 Projects:
Architectural Selection for all Group 3 projects have been completed; recommendation will be presented to the Board of Education on June 15, 2015.
Educational Specification Committee meetings will commence in June 2015.

Economic Inclusion:
The first class of the Jacobs Construction Academy was held on June 02, 2015.